Corporate News
-
31-03-2020
CMI RADES
November 25, 2018, HSRG modules of Unit #5 were delivered to Shanghai Port according to schedule.
-
31-03-2020
Delivery of NE OKPAI Porject HRSG Modules (2018.12.16)
December 16, 2018, HRSG Modules of NE OKPAI project for Nigeria end user were shipped to port. 2 units, total 16 modules. Besides the modules, all pipings were also within DNT's scope. Painting requirements are extremly high for these piping, sand blasting to grade SA2.5, inorganic zin-rich primer and silicone aluminium top coat are required as anti-corrosion. although it's very difficult to manufacture, packing and transport these products, DNT tried its best to conquer all dificulties and delivered the products with good quality within required time schedule.
-
31-03-2020
Delivery of Wuxi Boiler Iraq Basra Project Unit#1 HRSG Modules(2018.2.25)
February 25, 2018, 1st batch #1 Unit modules of Wuxi Boiler "One Road One Belt" Iraq Basra Project 650MW combined cycle power plant started delivering. 4 modules were loaded and delivered to Shanghai Port and will be shipped to Basra Iraq by sea.
-
31-03-2020
Delivery of Wuxi Boiler Iraq Basra Project Unit#3 HRSG Modules(2019.6.17)
On June 17th 2019, Wuxi Boiler Iraq Basra Project Unit#3 HRSG Modules started delivering, modules were delivered to Shanghai port according to schedule.
-
31-03-2020
Delivery of 9F Grade HRSG Modules of Shanghai Boiler ZHENJIANG 1# Unit(12.20.2019)
Jiangsu Zhenjiang Gas Turbine Cogeneration Project is a kind of clean energy State-encouraged project with outstanding energy saving efficiency. Jiangsu Province, Zhenjiang City and Dantu District governments are all focused on this project and listed it as the Key project of the National South Jiangsu Demonstration Zone.
-
31-03-2020
Successful Erection of DNT Manufactured HRSG Modules for CMI RADES Project
Successful Erection of DNT Manufactured HRSG Modules for CMI RADES Project.
-
31-03-2020
Delivery of CMI RADES Project HRSG Modules
RADES project is the first project that was signed between DNT and CMI, It takes two year from factory Audit to supplier qualification due to strict requirements from CMI. Since it's the first project, it is extremly inportant to DNT.
-
31-03-2020
Delivery of Wison Ethylene Cracking Furnace Convection Section Modules
Capacity of the unit is 1.4 million tons per year and is one of the world's largest.